What follows is what the Auditor-General of Pakistan has recorded about MM Pakistan (MMP) and the Chairman of the Pakistan Engineering Council (PEC). These are audit observations. Management disputed some, did not reply to others, and no court or tribunal has made a finding.

In paragraph 1.5.19 of the Audit Report for 2025-26, signed on 24 February 2026, the audit examines a Rs3,269.7 million consultancy contract signed on 9 September 2024 for 48 months. MMP led a joint venture with China Water Resources Beifang Investigation, Design and Research Co. Ltd. (BIDR) and was selected by direct selection. The audit gives five grounds. First, no emergency was declared by the project authorities or recognised by the World Bank. Second, MMP had been only a sub-consultant under Mott MacDonald Limited, which had defaulted, so retaining it was irregular. Third, the selection was made without evaluating technical capability, and the key-position criteria were lowered: experience from 1,000 MW to 500 MW, and key-expert experience from seven years to three. Fourth, in the audit’s words: “Mr. Waseem Nazir, Chairman, PEC is co-owner of M/s MMP. This dual role reflected a conflict of interest, as he was expected to remain impartial in regulatory and advisory functions.” Fifth, the Project Manager who served under Tarbela 4 was nominated again for Tarbela 5 and appointed again under the new contract as an MMP key expert.

Management replied that key experts were included as required, that a World Bank No Objection Letter had been obtained, and that direct selection was used in an emergency to ensure continuity. The audit answered that the reply was not tenable and that “the firm did not possess the required expertise, therefore, the criteria was tailored to suit specific consultants.” The audit records no response from the Chairman himself, and management’s reply does not address the conflict-of-interest ground. The matter was taken up in August 2025 and reported to the Ministry in October 2025. The Departmental Accounts Committee met on 23 and 24 January 2026, and its minutes were not provided to audit. The audit recommends that the award be justified and that open competitive bidding be used for re-hiring.

Also Read: Gohar Ejaz Backs S.M. Tanveer For FPCCI Presidency, Reveals Why Broader Business Alliance Failed

The same report criticises other MMP engagements. On the Warsak 2nd Rehabilitation (paragraph 1.5.18), the consultant said on 11 August 2023 that it could not continue and demobilised on 13 October 2023, with four of six supervision packages remaining and the final report not prepared. The contract was closed mutually with no claims, and the audit calls the absence of blacklisting an undue favour. It recommends an apex-level inquiry into who closed the contract. On K-IV (paragraph 1.5.35), Rs401.903 million was paid above the ceiling set in amendment No. 1, and the audit calls this not acceptable.

On Tarbela 5 itself (paragraphs 1.5.56 and 1.5.57), the audit records expenditure to FY2024-25 of Rs120,324.610 million against an approved PC-I of Rs82,361.600 million, an excess of 46.09 per cent. Civil works ran 152 per cent over and consultation and supervision 239.86 per cent over their PC-I provisions, with 25 variation orders issued. The audit cites “poor performance of the consultants and weak monitoring of the management.” It also records that consultant staff left site on 16 and 17 May 2024, that the termination notice was served without the 30 days’ notice the contract required, that claims potentially exceed USD 18 million, and that the lack of blacklisting is an undue favour.

The FY2024-25 report names the consultants at Tarbela in two further paragraphs. In paragraph 1.5.15, new trash racks costing Rs2,379.469 million were needed because the original racks were designed for 1,700 cubic metres a second instead of 2,100, and the audit holds the consultants responsible for approving the design. In paragraph 1.5.106, a variation order issued without the Employer’s consent led to payments of Rs211.184 million plus CNY 79.268 million, which the audit calls gross negligence of the consultants. Earlier, the Auditor-General’s performance audit of Tarbela 4 recorded a cost overrun of 47.1 per cent and attributed about Rs2.12 billion of variation payments, defective change orders and excess fees to the consultant joint venture that included MMP. MMP’s own share of the fees claimed above approved ceilings was Rs16.09 million.

Primary Document: AGP Audit Report on Ministry of Water Resources (Audit Year 2024-25)

About the author

The writer is water and climate change expert, is co-founder of Energy Excellence Centres at NUST and UET Peshawar